Bonded vs Unbonded Post-Tensioning: Which Fits

Bonded vs Unbonded Post-Tensioning in Concrete Structures

Bonded vs unbonded post-tensioning is settled once, at design, and every crew that later works on the structure has to deal with that choice. At Freyssinet USA, our post-tensioning teams inspect, repair and replace both types of tendons.

On an existing slab or bridge, the post-tensioning has to be located before any coring, sawing or drilling, since a cut through stressed steel can release its force at once. When the design criteria pull in different directions, chloride exposure and the maintenance plan usually settle the choice.

What Is the Difference Between Bonded and Unbonded Post-Tensioning?

The difference between bonded and unbonded post-tensioning is the filler around the strands: a cement-based fill locks a bonded tendon to the concrete along its full length, while a greased sheath leaves an unbonded strand free to slide between its end anchorages.

Attribute Bonded post-tensioning Unbonded post-tensioning
Filler Cementitious grout injected after stressing Corrosion-inhibiting grease, or a flexible filler such as wax in multistrand tendons
Tendon type Multistrand tendons or bars in a corrugated duct Mostly monostrand: one 7-wire strand in an extruded sheath
Force transfer Along the full length, through the bond Through the end anchorages only
Typical structures Bridges, segmental box girders, tanks Suspended floor slabs in buildings, parking structures, slabs on grade
Inspection access Steel hidden by the grouting: non-destructive methods and small openings Strand reached through exploratory openings in the sheath
Replacement Whole tendon replaced, or voids re-injected Monostrand de-tensioned, pulled out and replaced

This single property sets the inspection method for the tendons and the way a post-tensioning repair is planned decades after construction.

Bonded Tendons in Grouted Ducts

A bonded tendon is a group of 7-wire strands, or a high-strength steel bar, placed in a corrugated duct cast into the concrete. Multistrand tendons of this type typically hold 4 to 37 strands, locked together at each end.

Grouting is a separate step of the construction process. After stressing, the crew pumps cementitious grout around the strands, and once it hardens, steel and concrete act as one section. This step takes place on site, so its quality depends on the crew.

Unbonded Tendons in Greased Sheathing

An unbonded tendon is most often a monostrand: one 7-wire strand coated with corrosion-inhibiting grease and placed inside an extruded plastic sheath.

A wedge anchorage holds the strand at each end, encapsulated in current construction and often exposed in older slabs.

Older buildings may also hold 2 less common unbonded tendons, each inspected differently:

  • Paper-wrapped wire tendons: older unbonded tendons made of parallel wires in a greased paper wrap, held by button-head anchorages.
  • Multistrand unbonded tendons: several strands in one casing filled with a flexible filler such as wax instead of a cement mix.

How Does Post-Tensioning Work With Bonded and Unbonded Tendons?

Post-tensioning works the same way with both tendon types, a construction method providing compression where concrete needs it: in bonded and unbonded post-tensioned concrete alike, stressed strands put the concrete in compression and offset the tension that loads create.

Concrete has a high compressive strength but a low tensile strength, so the prestressing force keeps it in compression under service loads.

A hydraulic jack applies that tension once the concrete is strong enough, and the anchorages then pass it to the member in 2 different ways:

  • Bonded: the strands share strain with the concrete at every section along their length.
  • Unbonded: the strand acts on the member only through its end anchorages, and its stress spreads evenly over its full length.

Bonded Tendons Under Load

Under load, a bonded tendon strains with the concrete at every crack, which gives the structural engineer 3 benefits:

  • The strands develop a higher stress at ultimate load than in an unbonded member of the same size, which raises the flexural strength.
  • They control crack widths much like steel reinforcement.
  • A local loss of prestressing force stays confined to a short length of the member.

Fire performance follows the same logic: overheating weakens bonded strands only where the heat reaches them.

Unbonded Tendons Under Load

An unbonded tendon stretches over its whole length under load, so a crack at one section barely changes the strand stress.

At ultimate load, the same steel gives less flexural strength than in a bonded member.

The design adds bonded steel reinforcement to control crack widths in the slab and beams, a need specific to post-tension construction without bond.

The anchorages carry the full prestressing force for the life of the member. A corroded or broken anchorage releases that force along the whole strand, so engineers check the anchorages first in any assessment of an unbonded slab.

Which Post-Tensioning System Resists Corrosion Better?

Neither form of post-tensioning has a built-in corrosion advantage, because both protect the steel with successive layers.

The Post-Tensioning Tendon Installation and Grouting Manual of the FHWA describes these layers as the concrete cover, the duct or sheath, and the filler around the strands. Each layer fails where water reaches the steel through a gap.

Water, chlorides and oxygen need a path through all 3 layers before the steel starts to rust, so good detailing and sealing count as much as the choice of filler.

How Cementitious Grout Protects Bonded Tendons

Cementitious grout protects bonded tendons by blocking water and by keeping the steel passive:

  • Barrier: the cured filler keeps water, oxygen and carbon dioxide away from the strands.
  • Chemistry: its high pH forms a passive film on the steel, which stops rust from starting.

That chemical protection has 2 limits. Chlorides break down the passive film, and carbonation lowers the pH below about 9, where the film no longer holds.

Both reach the strands only where the grouting is missing, cracked or contaminated.

How Greased Sheathing Protects Unbonded Tendons

Compared with grouting, the greased sheathing isolates the strand without bonding it to the concrete. The coating covers the steel and the sheath keeps water out, so the protection lasts as long as both stay continuous.

The protection breaks at 4 typical points:

  • A sheath torn during placing or casting, which leaves the steel bare.
  • A gap where the sheath ends at the anchor.
  • An exposed anchorage, common in older slabs and parking structures.
  • An older paper-wrapped tendon, whose wrap gives little resistance to water and chlorides.

How Does Complete Grouting Prevent Voids in Bonded Post-Tensioning Tendons?

A duct filled from its low point with a non-bleeding mix leaves no space where water can collect, and that is how complete grouting keeps voids from forming.

Observed post-tensioning tendon corrosion goes back to water or moisture and to grouting voids, so full filling removes the main path to the steel.

Voids form at the high points of the profile, in sealed ducts and at poorly sealed end caps:

  • High points of the tendon profile: air and bleed water rise there, and the fill fails to reach the crown.
  • Sealed ducts: water that separates from the mix during curing stays trapped against the strands.
  • Poorly sealed anchorage caps: chlorides get in, a serious risk on coastal bridges and on decks treated with de-icing salts.

Complete post-tension grouting closes these voids with a non-bleeding material, vents at the high points and a check of every filled duct.

What Happens When a Post-Tensioning Tendon Is Cut or Damaged?

A bonded post-tensioning tendon that is cut or damaged loses its force only near the break, while an unbonded tendon loses it along its full length.

The grout acts as a second anchorage. It grips the bonded strands within a short distance on each side of the cut, while an unbonded strand has nothing to hold it between its ends.

The stored energy of an unbonded strand is the main safety risk. A released strand may burst out at the anchorage or through the slab, and the whole span it served loses that force at once.

Warning: coring, sawing or drilling a post-tensioned member can cut through stressed steel, so a post-tensioning specialist locates the tendons and plans the work first.

Where Are Bonded and Unbonded Post-Tensioning Systems Used?

Bonded post-tensioning mostly serves bridges and heavy civil structures across the United States, while unbonded post-tensioning is the usual choice for building slabs and parking structures.

Greased and sheathed monostrand is used mainly in building construction and only rarely in bridges, where grouted multistrand tendons are the norm in bridge construction.

Structure Usual tendon type Why
Bridge decks and segmental box girders Bonded multistrand tendons Redundancy, heavy repeated loads, exposure to de-icing salts
Tanks Usually bonded multistrand tendons Crack control under internal pressure over a long service life
Containment structures Either type; greased tendons where the tendons must stay inspectable Long-term monitoring of the prestressing force
Suspended floor slabs in buildings Unbonded monostrand Thin slabs, long spans, fast floor cycles
Parking structures Unbonded monostrand, encapsulated in current construction Thin slabs and beams; de-icing salts call for encapsulation
Slabs on ground Unbonded monostrand Fewer joints and crack control over large areas

For new structures, the post-tensioning systems specified today range from encapsulated monostrand for building construction to multistrand and bar tendons for bridges and heavy civil engineering works.

How Are Bonded and Unbonded Post-Tensioning Tendons Inspected?

Bonded and unbonded post-tensioning tendons are first located and identified, then checked with non-destructive methods when grouted and through direct openings when greased.

The scope of a post-tensioning inspection program covers the anchorages, the strands and their protection, and the remaining force of the tendons.

Crews reach the tendons by scaffolding or access platforms, and the stay cables of a cable-stayed bridge follow a separate program.

Identifying the System in an Existing Structure

To identify the tendons of an existing structure, engineers start with the record drawings and specifications. When those documents are missing, 3 clues tell bonded from unbonded:

  1. The anchorage pockets at slab edges or beam ends, whose size and spacing differ between monostrand and multistrand anchorages.
  2. A small exploratory opening, planned by a specialist, which shows either a corrugated duct with grout or a sheath with grease.
  3. Ground penetrating radar, used to locate the tendons and their profile before any opening.

Inspection Methods for Bonded Tendons

Bonded tendons are inspected with non-destructive methods, because the hardened fill hides the steel:

  • Impact echo and ultrasonic pulse velocity along the tendon path detect voids around the strands.
  • Borescope inspection through small drilled openings shows the strands inside a void.
  • Magnetic flux leakage detects broken wires and loss of steel section.

The results are mapped along the tendon profile before any re-injection or replacement is scheduled, since the repair method depends on them.

Inspection Methods for Unbonded Tendons

Exploratory openings give direct access to an unbonded tendon, exposing the strand, its coating and the sheath. The inspector checks whether the coating still covers the steel, whether moisture sits inside the sheath, and whether the anchorages are exposed or corroded.

A lift-off test using a hydraulic jack at the anchorage, or a lateral load test on the exposed strand, measures the tension left in the strand. Each opening is then restored so the protection stays continuous.

Can Bonded and Unbonded Post-Tensioning Tendons Be Replaced?

Yes, bonded and unbonded post-tensioning tendons can both be replaced, and the tendon type sets the method.

The work ranges from one strand at a time to a full multistrand replacement:

  • Unbonded monostrand: de-tensioned, pulled out of its sheath and replaced strand by strand, often while the rest of the slab stays in use, a process repeated for each damaged strand.
  • Bonded multistrand: replaced as a whole, or restored by re-injecting their voids when the strands are still sound.

Replacing a grouted tendon means releasing its force, removing it and building a new one in the same place:

  1. The corroded tendon is de-tensioned and removed.
  2. New strands are installed in its place.
  3. The replacement tendon is stressed, then grouted, so it can restore the capacity the corroded tendon had lost.

We followed that sequence to replace 2 corroded 1,000-foot tendons on the Wando Bridge in Charleston, South Carolina.

How Do Engineers Choose Between Bonded and Unbonded Post-Tensioning?

Engineers choose bonded post-tensioning for exposed, heavily loaded structures such as bridges, and unbonded post-tensioning for thin building slabs on a fast schedule.

For the structures between these 2 extremes, 4 criteria decide: exposure to chlorides, redundancy, member thickness and schedule, and future inspection and replacement.

Criterion Favors bonded when Favors unbonded when
Exposure to chlorides and water The member faces de-icing salts or sea spray and grouting quality is assured The slab is interior, or the tendons are encapsulated with watertight anchorages
Redundancy and crack control A local loss of force must stay local and crack widths must stay small Bonded reinforcement can take over crack control
Span and loads Loads are heavy and repeated, as on bridges Building loads act on long, thin slabs
Member thickness and schedule Members have room for ducts and the schedule allows a grouting step Slabs are thin and floor cycles are fast
Grouting quality control on site A qualified grouting crew and inspection are available Grouting quality would be hard to secure on the project
Future inspection and replacement Non-destructive inspection is planned over the service life Strands should stay accessible and replaceable one by one

When the criteria point in different directions, the exposure and the maintenance plan usually decide, because they govern the service life of the tendons and their advantages over time.

Compare Bonded and Unbonded Post-Tensioning on Your Structure With Freyssinet USA

Knowing which tendons a structure holds, and in what condition they are, is the starting point of any repair or change of use. At Freyssinet USA, we identify bonded and unbonded tendons, assess their protection and remaining force, and plan their repair or replacement.

We carry the name of the engineer who patented post-tensioning in 1928, and our group invented the greased and sheathed strand in 1975.

Request a post-tensioning assessment of your structure.

Frequently Asked Questions About Bonded and Unbonded Post-Tensioning

Does Bonded or Unbonded Post-Tensioning Allow Longer Spans?

Neither type sets the span by itself in post-tension design. The span comes from the prestressing force, the tendon profile and the member depth chosen by the designer, and both types reach long spans: unbonded tendons in long-span slabs, bonded tendons in bridge girders.

Are the Tendons in a Bonded Post-Tensioned Slab Coated With Grease?

No, a bonded post-tension slab uses grouted tendons without any grease. Its strands typically sit side by side in flat ducts sized for the slab thickness, and the belief comes from the greased monostrand found in most building slabs.

Are External Post-Tensioning Tendons Bonded or Unbonded?

External tendons run outside the concrete section, between anchorages and deviators, so they are structurally considered unbonded. This holds even when their polyethylene pipe is grouted, because the fill there only protects the steel.

How Long Does a Post-Tensioned Structure Last?

A post-tensioned structure lasts as long as the corrosion protection of its tendons holds, so no single service life applies. That protection depends on complete grouting for bonded tendons and on intact sheathing and anchorages for unbonded tendons, both kept in check by periodic inspection.